Public charging station maintenance: SLA, faults and availability (2026)

What public charging station maintenance includes, what the Electricity Administration and the Electricity Authority require, what to put in an SLA and how OCPP monitoring shortens downtime. A guide for site owners and operators.

Updated: November 2026

In short: Public charging station maintenance has three layers: real-time remote monitoring (OCPP), on-site preventive maintenance and fault repair according to response times set in a service level agreement (SLA). Under the Electricity Administration guidelines, the station owner is responsible for maintenance, and under the Electricity Authority rules, the information on station availability must reflect its working condition.

A public charging station that doesn't work is not just lost revenue. A driver who arrives at an out-of-service station won't come back, a negative review in the app stays there, and the site owner gets the complaints. That's why anyone setting up stations in a parking facility, fuel station, mall or local authority should plan maintenance at the purchasing stage, not after the first fault. This guide is for site owners, operators and property managers, and explains what maintenance includes, what the law requires, what to put in an SLA and how remote monitoring shortens downtime. For the full picture of setup and management, see our page on Setting up public charging stations.

What does public charging station maintenance include?

Public charging station maintenance is everything needed to keep the station available, safe and collecting payment properly. It is divided into three layers that work together, and when one of them is missing, it quickly shows up in availability.

  • Remote monitoring: A cloud management system that receives the status of each station (available, charging, faulted, disconnected) and sends an alert when something goes wrong.
  • Preventive maintenance: Scheduled site visits to check cables, connectors, sealing, cleanliness and panel protections, before a small fault turns into downtime.
  • Corrective maintenance: Handling a fault that has already occurred, first remotely and, if needed, by sending a technician, according to defined response times.

What does the law require for public charging station maintenance?

Two bodies set the rules. The Electricity Administration sets the safety requirements for the installation, and the Electricity Authority sets the station operator's obligations toward customers. Under section 16 of the Electricity Administration's “Guidelines for Installing an EV Charging System” (25.11.2025), the owner of the charging system is responsible for its maintenance even after installation.

When What's required Source
At least once a year The station owner presses the RCD test button and visually inspects the station Electricity Administration, section 16(a)
Once every six years An electrician performs an inspection and tests the RCDs with a suitable instrument Electricity Administration, section 16(b)
When a dangerous defect is found Immediate disconnection, and do not reconnect until repaired and inspected by an inspecting electrician Electricity Administration, section 16(g)
After a fundamental change (for example, replacing the charger model) Re-inspection by an inspecting electrician and an inspection report Electricity Administration, section 15
From 26.7.2026 A licensed operator (8 megawatts and above) maintains customer service for faults and safety and publishes the station's price, type and availability online. The availability information must reflect the station's working condition Electricity Authority, decision 73006
From 26.7.2026 An operator exempt from licensing must also allow charging to be stopped at any time and comply with the Ministry of Energy's cyber guidelines for grid-connected stations. The price publication requirement applies to it from 1.1.2028 Electricity Authority, decision 73006

DC fast charging stations have another component that needs maintenance: the credit card payment terminal. Under decision 73006, new fast charging stations put into operation from 1.1.2027 must allow payment by terminal from the start of operation, and all fast charging stations from 1.1.2028. A terminal that doesn't work means a station where you can't pay. Full details of the installation requirements are in the guide Charging station installation guidelines, and on-site testing methods in the guide Charging station inspection.

What is checked during preventive maintenance of a charging station?

Preventive maintenance focuses on components that wear out or are exposed to damage in daily use. The frequency is set by the model's maintenance instructions, usage load and environmental conditions: a station in a covered underground parking garage wears differently from an exposed station at a fuel station near the sea.

Component What to check Why it matters
Cable and connector Cracks in the insulation, burnt or bent pins, locking latch A faulty connector causes overheating and charging interruptions, and in a dangerous case requires immediate disconnection
Enclosure and sealing Gaskets, doors, cable entries, signs of water ingress DSGCharge public charging stations are rated IP55, and the sealing is maintained only when the gaskets are intact
Supply panel and protections The RCD test button, tightening connections, signs of heat This is the annual check the guidelines require, and a loose connection is a common cause of overheating
Communication 4G signal strength or LAN connection stability, last connection time to the cloud A station disconnected from the cloud doesn't report status and sometimes doesn't authorize charging
Payment and identification RFID reader, credit card payment terminal, QR code, screen A driver who can't start charging sees an out-of-service station, even if the power is fine
Cooling (in DC stations) Cleaning filters and vents, checking that fans work Blocked cooling reduces power output and may take the station out of service on hot days
Signage and surroundings Visible support center number, price signage, wheel stops and lighting The Electricity Authority rules require the price to be posted next to a fast charging station, and clear signage speeds up fault reporting

How does OCPP remote monitoring shorten fault time?

OCPP (Open Charge Point Protocol) is an open protocol through which the charging station communicates with a cloud management system. In version 1.6, the station sends a status message on every change of state, and the system can reset it remotely, request a diagnostics file, update firmware and mark it as unavailable. In practice, this means many faults are detected and handled before a driver complains.

  • Instant alert: The station reports “faulted” or stops reporting, and the support center sees it on the dashboard.
  • First response remotely: A reset, checking the fault log and changing settings solve some faults without a site visit.
  • Targeted visit: When a technician is needed, they know in advance what the fault is and which part to bring.
  • Real availability in the app: A faulted station is marked as unavailable, as the Electricity Authority rules require.

We have written in detail about the benefits of OCPP managed stations for business owners. All DSGCharge public charging stations are managed with OCPP from a cloud system.

What is an SLA for charging stations, and what should it include?

An SLA (Service Level Agreement) is an annex to the service contract that defines the service level in numbers: how much of the time the station must be available, how quickly faults are handled and what happens when the target is not met. Without an SLA, “service” is a general promise that is hard to enforce.

These are the clauses worth defining:

  • Availability target: The percentage of time the station is available for charging, and how it is measured. It is important to define in advance what does not count as downtime, for example a power outage by the IEC or a non-electric vehicle parked in the space.
  • Response time: How quickly work on a fault begins, remotely and on site.
  • Repair time: How quickly the station is back in operation, distinguishing between a fault that takes the whole station down and a fault in a single connector.
  • Support center hours and reporting channels: Phone, app or a QR code on the station.
  • Preventive maintenance: How many visits a year and what is checked on each visit.
  • Spare parts and reports: Who holds inventory, and a monthly availability and fault report.

To understand what an availability target means, here is the calculation of allowed downtime for each target, for a station that is supposed to operate 24 hours a day:

Availability target Allowed downtime per year Allowed downtime per month (average)
95% About 438 hours (about 18 days) About 36.5 hours
97% About 263 hours (about 11 days) About 22 hours
98% About 175 hours (about 7.3 days) About 14.6 hours
99% About 88 hours (about 3.7 days) About 7.3 hours

The calculation: 8,760 hours a year multiplied by the percentage allowed for downtime. The difference between 95% and 99% is two full weeks of downtime a year, so it pays to choose a target that suits the type of site. At a fast charging site on a highway, where drivers depend on the station, the target should be higher than in a parking facility with many AC stations.

What are common faults in public charging stations, and how are they handled?

Most faults in public charging stations fall into a few recurring types. The important distinction is between a fault that can be solved remotely and one that requires a technician or electrician on site.

Fault What it looks like First response
Communication loss The station appears as disconnected on the management dashboard Remote reset if possible; on site, check the SIM card, signal or router
Identification or payment fault The driver can't start charging, the power is fine Check in the management system (permissions, tariff, payment processing); on site, check the reader or terminal
RCD that trips The station is off or shuts down in the middle of charging Electrician visit: check for leakage current, the breaker type and the connections
Faulty cable or connector Visible damage, overheating, charging that stops Mark the station as unavailable remotely, disconnect and replace on site
Slower charging than expected Lower than usual power Check the load management settings and current limit remotely; in DC stations, also check the cooling
Physical damage or vandalism Broken screen, damaged enclosure Disconnect if there is a hazard, and replace the part on site

Warranty or service contract: what's the difference?

A warranty is the supplier's commitment for the product itself: if a component in the station fails during the warranty period, it is repaired or replaced according to the warranty terms. A service contract defines everything else: monitoring, preventive maintenance, response times and an availability target. A public charging station needs both.

Product or service Price (as of November 2026) Note
DSG-6052 Public dual charging station 22kW ₪6,990 24-month warranty, IP55, Wi-Fi, LAN and 4G
DSG-6112 Dual free-standing public station 22kW ₪7,990 (instead of ₪9,900) 24-month warranty, IP55
DSG-5260 Public DC station 60kW ₪34,990 24-month warranty, LAN and 4G, credit card payment terminal as an option
DSG-7420 Ultra-fast DC station 120kW By quote 24-month warranty, extendable for an additional fee
DSG-9909 Out-of-warranty technician service call ₪590 Visit within 3 business days of ordering

Prices according to the DSGCharge store. A single service call suits one station at home or in a small business. For public charging stations, where every hour of downtime costs money, a service contract with an SLA is recommended. More on warranty terms in the guide Charging station warranty.

How much does public charging station maintenance cost?

There is no single price for maintenance, because the cost depends on several factors: the number of stations and their type (AC or DC), the availability target and response times in the SLA, the distance between sites, support center hours, and whether cloud monitoring and the payment processing system are included. DC stations are more complex than AC stations and require broader preventive maintenance, partly because of the cooling system and the payment terminal.

When planning the budget, it is worth calculating maintenance as part of the site's total cost, alongside the hardware, infrastructure and the electrical connection. A full cost breakdown is in the guide How much does it cost to set up a fast-charging station, and on choosing a fast charging station by location in the guide Ultra-fast charging station.

Who maintains DSGCharge public charging stations?

DSGCharge is one of Israel's leading companies in EV charging solutions. DSGCharge is the importer of its charging stations – the brand is DSGCharge's own – so service, spare parts and warranty come from one source. The company has been active since 2021, and about 20,000 chargers and charging stations have been sold and installed to date, with installation and service teams nationwide. The products hold Standards Institution of Israel (SII) approvals.

For public charging stations, DSGCharge provides Public charging station management system in full: cloud management with OCPP, fault monitoring, an app, payment terminals, license plate recognition cameras and reports. The system is developed in-house by DSGCharge and can be customized and branded to the customer's requirements (White Label). This way, the same team that installs the stations also sees their status in real time and handles faults. In the partnership model for site owners, there is no financial investment on the site owner's part; revenue sharing is set according to the location and subject to a feasibility check. You can estimate the installation cost with theCharging station installation cost calculator.

Frequently asked questions about charging station maintenance

Who is responsible for maintaining a public charging station?

Under section 16 of the Electricity Administration guidelines (25.11.2025), the owner of the charging system is responsible for maintenance even after installation. In practice, the owner hands over the work to a supplier or operator under a service contract.

How often should a public charging station be inspected?

Under the guidelines, an RCD test and a visual inspection at least once a year, and an electrician's inspection once every six years. For a public charging station, it is worth setting more frequent preventive maintenance visits in the contract, according to the model's instructions and usage load.

What is an SLA for charging stations?

An annex to the service contract that defines an availability target, response time, repair time and support center hours. For example, a 98% target allows about 175 hours of downtime a year, and a 99% target allows about 88 hours.

Does a station operator have to run a fault support center?

Under Electricity Authority decision 73006, a license holder (cumulative capacity of 8 megawatts and above) must maintain customer service for faults and safety and publish station availability online. An exempt operator is not explicitly required to do so, but an available support center is a basic part of any good service.

What does the warranty on DSGCharge public charging stations include?

According to the product pages, the public charging stations come with a 24-month warranty, and on the ultra-fast stations it can be extended for an additional fee. An out-of-warranty service call, DSG-9909, costs ₪590 (as of November 2026).

Want a maintenance plan for your stations?

The DSGCharge team will build a maintenance plan and SLA with you that suit the type of site and the number of stations, for new or existing stations. leave your details or call 077-9920350.

Sources: Electricity Administration, “Guidelines for Installing an EV Charging System” (25.11.2025), sections 15 and 16; Electricity Authority, decision 73006 (31.12.2025, in effect from 26.7.2026); Open Charge Alliance, OCPP 1.6 specification. Prices and specifications according to the DSGCharge store. All information is accurate as of November 2026.

Share the article:

Already more than

0 +

stations installed

Let us help you

We promise to get back to you in record time with a winning offer!

Which product are you interested in?
  • The cost of a home charging station varies by brand and the station's charging power. There are three charging station power levels: 7kW, 11kW, 22kW (single-phase).

    7kW charging stations are recommended for charging plug-in hybrids (gasoline/diesel-electric) and/or cars that can't charge on three-phase. They aren't recommended for charging an EV, since the time needed to charge an EV will be long. 

    The price of charging stations is affected not only by the station's power but also by whether it has a display and whether it's a smart station managed through a mobile app.

    The price of a simple charging station starts at about ₪1,690 (a promotion at our company for a smart three-phase charging station. The lowest price in Israel!) for 11kW and can reach about ₪4,200 for a 22kW smart station. 

    The price of public charging stations is completely different and is affected by the charging rate, the ability to communicate with computer systems and billing systems. 

    The price of a fast (DC) station runs from tens to hundreds of thousands of shekels.

    The prices above refer to the charging station only and do not include installation. 

  • The cost of charging an EV is significantly lower than fueling a car with a combustion engine (gasoline/diesel). The price per kWh on the residential tariff is 62 agorot (06/2024).

    The cost of driving an EV is around 10% of the cost of driving a combustion-engine car, and that's before accounting for routine servicing, which an EV doesn't need.

    The price of public charging is higher than home charging and is around ₪2.5 per kWh. Despite the higher price at a public station, charging at a public station is still about 60 percent cheaper than fueling a combustion-engine car.  

    There's no doubt that electric charging costs allow cheap driving and may save about ₪15,000 a year, based on driving 20,000 km a year.

    In addition to the savings on driving costs, it's important to emphasize that the annual license fee for an EV is ₪537, while the annual license fee for a combustion-engine and/or plug-in car can reach ₪4,700.

    Bear in mind that the state has already announced that in 2025 a mileage tax (15-25 agorot) will be imposed on EVs. The tax will probably be paid according to the car's odometer at the annual inspection. Even after the mileage tax is imposed, there will be large gaps in driving costs.

  • The cost of installing a home charging station varies by installation location, existing infrastructure, the distance between the electrical panel and the charging station, and the construction work required.

    A distinction should be made between installation in a private house (ground level) and installation in an apartment building. 

    Installation in a private house is simpler, but it too may require laying infrastructure, construction work, chiseling and adjustments.

    Installation in an apartment building is different: it requires a survey of the installation site (virtual/physical) and a signed confirmation that the building committee does not object to the installation. Installation costs in an apartment building are higher than in a private house, and in most cases installation requires construction work, chiseling and adjustments.

    A basic installation starts at ₪2,990 and can reach higher amounts depending on the installation requirements.

    The basic installation price includes laying up to 30 meters of cable. Each additional meter requires an extra charge depending on the station type. In every installation the company installs components in the electrical panel, a circuit breaker and an RCD (Type A), and near the charging station we install an isolating switch. All the company's charging stations are protected against DC leakage current. 

    According to the customer's needs, a meter (kW) can also be installed. A meter is needed when the electricity feeding the station comes from the building's general electrical panel and the building committee must be paid for the electricity consumed. It's important to emphasize that the building committee is not obligated to agree to powering the charging station from the common panel. 

    Each customer can decide whether they want installation by the company and/or prefer to install independently through a certified electrician.

    Installation by the company extends the station's warranty by another year, i.e. 12 additional months.

  • We've encountered quite a few cases where customers living in older houses have a single-phase home electricity network.

     

    The question is whether an EV can be charged from a single-phase home network. The answer is yes, but charging will be slower.

     

    A separate line from the panel must be laid to the charging station. A 16A line allows charging at 3.68kW per hour. A 25A line allows charging at 5.75kW per hour and a 32A line allows charging at 7.4kW.

    EV batteries are typically between 50-80 kWh. 

    This means that if the home had three-phase electricity the car would charge in 5-7 hours, while on a single-phase home network the car can be charged

    16 – 21 hours on a 16A line

    10 – 14 hours on a 32A line.

    Needless to say, the car is usually charged when the battery is around 50%, so the car can also be charged on a home network within one night. 

  • The charging time of the car battery varies by the charging infrastructure and the size of the car's battery.  

    Plug-in hybrid batteries are small batteries that charge on 3.7kW single-phase charging stations within up to three hours. 

    EVs are equipped with larger batteries that can exceed 80kW in cars with a driving range of about 450 km. 

    95% of cars on the market today support a charging rate of 11kW. 

    For a car to charge at a faster rate, two conditions must be met together: 

    A. The car can charge at a rate of 22kW.

    B. The electricity network supports charging at 32A and above, i.e. three-phase 40A and above. 

    However, you can ask the IEC to upgrade the infrastructure, allowing the use of more powerful charging stations: 22kW. 

    Even if the electricity feed currently supports three-phase 25A, it can be expanded through the IEC. The estimated cost of expanding from 25A to 40A is about ₪3,000. 

    All of the above isn't relevant to fast (DC) charging stations, which operate at high charging power of 30-350kW. These stations allow charging about 80 percent of battery capacity within minutes.

  • Deciding the charging station location is an important decision that should be guided by where the car parks and the existing infrastructure.

    The distance of the charging station from the electrical panel matters, as do the car's parking spot and the length of the station's cable, which is usually limited to five meters. 

    If you don't park the car in covered parking, the station needs a high level of water and dust sealing: IP54 and above. At our company all stations are resistant to rain and weather conditions. 

    If the station is installed outside the house, it's important to know that a charging pedestal will usually be needed, and its installation involves an extra charge. 

  • A three-phase connection at home isn't mandatory. There are single-phase charging stations that will charge the car, but charging with them will be slow. Single-phase charging stations are mainly suited to plug-in hybrids.

    If you have the option and the home's infrastructure allows a three-phase connection, it's better to install a three-phase charging station. Such a station allows fast charging of the car. 

    If your car requires a single-phase charging station, chances are that your next car will already need a three-phase charging station, so we recommend saving a future installation and station replacement by installing a three-phase charging station today.

  • When choosing a station, you must take into account:

    1. Is it a fully electric car or a plug-in hybrid: If the car is fully electric, a three-phase station should be installed. If the car is a plug-in hybrid, a single-phase station is enough. 
    2. Does the station include a holder for the charging cable: Stations that provide space for coiling and storing the cable protect it from wear and damage. 
    3. Locking mechanism: If the station will be located outside the house, it's important that it can be locked.
    4. Size and appearance: This is of course a matter of personal taste, but since there's a wide range of charging stations there's no reason to compromise on appearance. 
  • The IP rating is a classification of the degree of protection and sealing of the station against dust and water. The rating consists of the letters IP and two digits, defined by the IEC 60529 standard of the International Electrotechnical Commission. The first digit rates sealing against dust and the second digit rates sealing against water.

    IP54: dust can enter but doesn't interfere with the station. The station is sealed against water at 10 liters/minute at a pressure of 80-100 kilopascals. 

    IP55: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP65: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP67: dust doesn't enter the station. The station is resistant to immersion in water at a depth of 1 meter for 30 minutes.

    Stations installed in an uncovered location should have a sealing level of IP55-67.

  • All the company's products are sold with a 24-month warranty, with the option to extend the warranty up to 60 months.

    If the station is installed by the company's installation team, the customer receives a gift of 12 additional warranty months, for a total of 36 months of warranty. 

    The company allows extending the warranty on stations up to 60 months.

    Because the company is confident in the quality of its products, which have been sold in Europe for many years (France, Germany and more), it offers a warranty extension at a nominal price of ₪499  for an additional 24 months. The warranty extension is possible up to 7 days from the station installation date. 