Charging station testing is part of every installation and every maintenance visit for an AC station, whether in a private home, an apartment building or a business parking facility. Anyone who installs or maintains stations needs to know what to test, when and with which instrument. This guide is for electricians and installers, as well as station owners, building committees and parking facility managers who want to understand what the electrician is supposed to check.

In short: Under the Electricity Administration guidelines (25.11.2025), an inspecting electrician inspects the charging system before first operation and after every fundamental change, covering 12 topics. The station owner tests the RCD once a year, and an electrician performs an inspection once every six years. In the field, an AC charging station tester (vehicle simulation) and a power quality and load analyzer are used.

If you're choosing a new station for your home, building or parking facility, you can compare all the models on the EV charging stations in the DSGCharge store.

What does charging station testing include?

Charging station testing includes three parts: testing the electrical installation that supplies the station, functional testing of the station itself against a simulated “vehicle,” and in some cases measuring power quality and loads in the panel. The first part is set by regulation, the second verifies that the station actually communicates with a vehicle and disconnects when it should, and the third is important mainly in buildings and parking facilities with several stations.

  • The installation: Panel protections, the supply route, earthing and its continuity, the RCD and DC leakage current detection.
  • The station: Transitions between charging states, response to communication and earthing faults, correct cable detection.
  • The grid: Voltage, current, harmonics, phase imbalance and load during charging.

What do the Electricity Administration guidelines require in the pre-operation inspection?

Section 15 of the Electricity Administration's “Guidelines for Installing an EV Charging System” (published on 25.11.2025) states that a charging system is inspected before its first operation and after every fundamental change, by an inspecting electrician holding a suitable license. The guidelines define a fundamental change as replacing the charger model, a change in the means of protection against electric shock, or a change in the supply circuit or cable cross-section.

The inspection covers 12 topics:

  1. Accredited laboratory approvals for the equipment and compliance with the standard.
  2. Compliance with the electricity regulations and the guidelines.
  3. The protective devices in the supply panel.
  4. The supply route to the station.
  5. Stable installation, mechanical protection and signage.
  6. The earthing system, including a local electrode if there is one.
  7. Earthing continuity up to the connection point.
  8. Protection against electric shock.
  9. RCD and DC leakage current detection.
  10. Overvoltage protection in stations for public use.
  11. Measurements at the vehicle connection points or at the station terminals, including proper operation of the protections.
  12. Testing vehicle-to-grid supply capability (V2X), if present.

The results are documented in an inspection report using the form published by the Electricity Administration, and the installer hands it over to the system owner (sections 15(b) and 17). A full explanation of all sections of the guidelines is in the guide Charging station installation guidelines.

Which RCD should be tested in a charging station?

Under section 6 of the guidelines, every AC connection point is protected by a dedicated RCD that trips at a residual current above 30mA. The RCD must be Type B, or Type A or F together with a means of detecting DC leakage current. The detection device can be built into the station, attached to it or in the panel.

During the inspection, it is important to verify which solution is actually in place. A station with a built-in DC detector and a Type A RCD in the panel is a valid configuration, but only if the detector actually exists in the installed model. DC leakage current is current that comes from the charger inside the vehicle, and a regular Type AC RCD may fail to detect it and may even be weakened by it.

Which instruments are used to test a charging station?

No single instrument does it all. An inspecting electrician uses an installation tester for earthing, insulation and RCD trip time tests. Alongside it, there are two dedicated instruments for charging stations: an instrument that simulates an electric vehicle and tests the station itself, and an analyzer that measures power quality and loads.

Device What is checked by Best for Price (as of November 2026)
AC charging station tester, model DSG-500 Vehicle simulation via a Type 2 socket, charging states A, B, C, D, communication fault (CP) and earthing fault (PE) simulation, cable resistance Installers, service technicians, inspecting electricians ₪1,190 (instead of ₪1,790)
Power quality and load analyzer, model DSG-10602 4 voltage channels and 4 current channels, harmonics up to the 50th, THD, power and energy per phase, imbalance, flicker, inrush current, long-term logging Electrical designers, management companies, buildings and parking facilities with several stations ₪17,990 (instead of ₪19,990)
Installation tester (multifunction) Earthing and continuity, insulation, RCD trip time and trip current an inspecting electrician The electrician's working equipment

Prices according to the DSGCharge store. All the instruments are in the category Testing equipment.

How do you test an AC charging station with a vehicle-simulating instrument?

An instrument like the DSG-500 connects to the station cable through a Type 2 socket and behaves like an electric vehicle. This lets you test the station without a car in the parking space and reproduce faults that are hard to reproduce with a real vehicle. The instrument works with both single-phase stations (up to 250V) and three-phase stations (up to 480V), with indicator lights for each phase and each state.

A typical work sequence:

  1. State A, not connected: Verify that the station is in standby and there is no voltage on the connector.
  2. State B, connected: The station detects a “vehicle” and signals the allowed current. In a managed charging station, this is also the moment to check authorization via RFID or the app.
  3. State C, charging: The station closes the contactor, and you check that there is voltage on all the phases that are supposed to work.
  4. State D, charging with ventilation required: Check that the station responds according to its settings.
  5. Fault simulation: Disconnect the communication line (CP) and the earth (PE) in simulation, and check that the station stops charging and displays a fault.
  6. Cable test: Measure the cable resistance and verify that the station detects it correctly.

States A to D are defined in the international standard IEC 61851-1, which describes the basic communication between an AC station and a vehicle: the station sends a signal on the CP line, and the vehicle changes the voltage on the line to indicate whether it is connected and ready to charge.

When do you need a power analyzer and not just a station tester?

A power analyzer is needed when the question is not “does the station work” but “can the power in the panel handle the load.” This happens mainly in an apartment building, parking facility or business with several stations, when planning to add stations, or when there are unexplained trips.

The DSG-10602 displays waveforms in real time, measures harmonics and THD, active, reactive and apparent power per phase, imbalance and flicker, and records inrush current. You can leave it in continuous logging: 20 parameters every second, for a period of about 300 days according to the product specifications, with a battery for about 8 hours of operation. This shows what happens in the panel during evening peak hours, when most vehicles plug in.

In buildings with a load management system, the measurement helps determine how much current can be distributed among the stations without increasing the connection size. Managed charging stations such as DSG-6012 are limited to the current set for them from the cloud, so it is important to base the setting on a real measurement.

How often should a charging station be inspected?

Under section 16 of the Electricity Administration guidelines, the owner of the charging system is responsible for maintenance even after installation. The table summarizes the intervals:

When Who What Section
Before first operation and after a major modification an inspecting electrician Inspection covering 12 topics and an inspection report 15
At least once a year Station owner Pressing the RCD test button and a visual inspection 16(a)
Once every six years Electrician, ordered by the owner System inspection and testing of the RCDs with a suitable instrument 16(b)
When the RCD is the only protection against electric shock Owner / electrician Button every six months, instrument test every two years 16(e)
When a dangerous defect is found Owners Immediate disconnection, and do not reconnect until repaired and inspected by an inspecting electrician 16(g)

Source: Electricity Administration, “Guidelines for Installing an EV Charging System,” 25.11.2025 (gov.il).

What do you check when a charging station isn't charging?

When a station isn't charging, the check starts with a simple question: is the fault in the station, the vehicle or the supply? A vehicle-simulating instrument answers this quickly: if the station passes all the states with the instrument, the problem is probably in the vehicle or its settings. If not, check the supply, the RCD and the cable.

  • RCD that trips only during charging: check for DC leakage current and the RCD type.
  • Slower charging than expected: check how many phases are working and what current the station is signaling.
  • Trips in the evening hours: check the load and voltage in the panel with an analyzer.

Owners of a home charging station have a separate guide with simple checks they can do themselves: Charging station not responding?. In cloud-connected stations, many faults are diagnosed remotely before anyone goes on site. This is one of the advantages of OCPP managed stations: fault log, connection status and current limit, all available from the office.

Who tests and maintains stations installed by DSGCharge?

DSGCharge is one of Israel's leading companies in EV charging solutions. DSGCharge is the importer of its charging stations – the brand is DSGCharge's own. The company has been active since 2021, and about 20,000 chargers and charging stations have been sold and installed to date, with installation and service teams across the country. The products hold Standards Institution of Israel (SII) approvals.

Beyond selling testing instruments, DSGCharge carries out EV charging station installation, setup and management of charging systems in buildings and parking facilities, and service for existing stations:

You can see all the products on the Charging stations and accessories, and estimate the installation cost with the calculator Charging station installation cost calculator.

Frequently asked questions about charging station testing

Who is allowed to inspect a charging station before operation?

Under section 15 of the Electricity Administration guidelines (25.11.2025), an inspecting electrician holding a suitable license. The inspection is required before first operation and after every fundamental change, and the results are recorded in an inspection report.

How often should a home charging station be tested?

The station owner presses the RCD test button and visually inspects the station at least once a year. Once every six years, an electrician performs an inspection and tests the RCDs with an instrument.

What does an AC charging station tester do?

It connects to the station cable and simulates an electric vehicle. This lets you test charging states A to D, the response to a communication fault and an earthing fault, and cable detection, without a vehicle in the parking space. The DSG-500 costs ₪1,190 (as of November 2026).

Does a station tester replace the inspecting electrician's inspection?

No. It tests the station itself. Earthing, insulation and RCD trip time are tested with an installation tester, and the official pre-operation inspection is carried out by an inspecting electrician.

Which RCD is required for a charging station?

A dedicated 30mA RCD for each AC connection point, Type B, or Type A or F with a means of detecting DC leakage current. The detection device can be built into the station (section 6 of the guidelines).

Need a testing instrument, installation or service for existing stations?
Leave your details in theContact or call 077-9920350, and the DSGCharge team will get back to you.

Share the article:

Already more than

0 +

stations installed

Let us help you

We promise to get back to you in record time with a winning offer!

Which product are you interested in?
  • The cost of a home charging station varies by brand and the station's charging power. There are three charging station power levels: 7kW, 11kW, 22kW (single-phase).

    7kW charging stations are recommended for charging plug-in hybrids (gasoline/diesel-electric) and/or cars that can't charge on three-phase. They aren't recommended for charging an EV, since the time needed to charge an EV will be long. 

    The price of charging stations is affected not only by the station's power but also by whether it has a display and whether it's a smart station managed through a mobile app.

    The price of a simple charging station starts at about ₪1,690 (a promotion at our company for a smart three-phase charging station. The lowest price in Israel!) for 11kW and can reach about ₪4,200 for a 22kW smart station. 

    The price of public charging stations is completely different and is affected by the charging rate, the ability to communicate with computer systems and billing systems. 

    The price of a fast (DC) station runs from tens to hundreds of thousands of shekels.

    The prices above refer to the charging station only and do not include installation. 

  • The cost of charging an EV is significantly lower than fueling a car with a combustion engine (gasoline/diesel). The price per kWh on the residential tariff is 62 agorot (06/2024).

    The cost of driving an EV is around 10% of the cost of driving a combustion-engine car, and that's before accounting for routine servicing, which an EV doesn't need.

    The price of public charging is higher than home charging and is around ₪2.5 per kWh. Despite the higher price at a public station, charging at a public station is still about 60 percent cheaper than fueling a combustion-engine car.  

    There's no doubt that electric charging costs allow cheap driving and may save about ₪15,000 a year, based on driving 20,000 km a year.

    In addition to the savings on driving costs, it's important to emphasize that the annual license fee for an EV is ₪537, while the annual license fee for a combustion-engine and/or plug-in car can reach ₪4,700.

    Bear in mind that the state has already announced that in 2025 a mileage tax (15-25 agorot) will be imposed on EVs. The tax will probably be paid according to the car's odometer at the annual inspection. Even after the mileage tax is imposed, there will be large gaps in driving costs.

  • The cost of installing a home charging station varies by installation location, existing infrastructure, the distance between the electrical panel and the charging station, and the construction work required.

    A distinction should be made between installation in a private house (ground level) and installation in an apartment building. 

    Installation in a private house is simpler, but it too may require laying infrastructure, construction work, chiseling and adjustments.

    Installation in an apartment building is different: it requires a survey of the installation site (virtual/physical) and a signed confirmation that the building committee does not object to the installation. Installation costs in an apartment building are higher than in a private house, and in most cases installation requires construction work, chiseling and adjustments.

    A basic installation starts at ₪2,990 and can reach higher amounts depending on the installation requirements.

    The basic installation price includes laying up to 30 meters of cable. Each additional meter requires an extra charge depending on the station type. In every installation the company installs components in the electrical panel, a circuit breaker and an RCD (Type A), and near the charging station we install an isolating switch. All the company's charging stations are protected against DC leakage current. 

    According to the customer's needs, a meter (kW) can also be installed. A meter is needed when the electricity feeding the station comes from the building's general electrical panel and the building committee must be paid for the electricity consumed. It's important to emphasize that the building committee is not obligated to agree to powering the charging station from the common panel. 

    Each customer can decide whether they want installation by the company and/or prefer to install independently through a certified electrician.

    Installation by the company extends the station's warranty by another year, i.e. 12 additional months.

  • We've encountered quite a few cases where customers living in older houses have a single-phase home electricity network.

     

    The question is whether an EV can be charged from a single-phase home network. The answer is yes, but charging will be slower.

     

    A separate line from the panel must be laid to the charging station. A 16A line allows charging at 3.68kW per hour. A 25A line allows charging at 5.75kW per hour and a 32A line allows charging at 7.4kW.

    EV batteries are typically between 50-80 kWh. 

    This means that if the home had three-phase electricity the car would charge in 5-7 hours, while on a single-phase home network the car can be charged

    16 – 21 hours on a 16A line

    10 – 14 hours on a 32A line.

    Needless to say, the car is usually charged when the battery is around 50%, so the car can also be charged on a home network within one night. 

  • The charging time of the car battery varies by the charging infrastructure and the size of the car's battery.  

    Plug-in hybrid batteries are small batteries that charge on 3.7kW single-phase charging stations within up to three hours. 

    EVs are equipped with larger batteries that can exceed 80kW in cars with a driving range of about 450 km. 

    95% of cars on the market today support a charging rate of 11kW. 

    For a car to charge at a faster rate, two conditions must be met together: 

    A. The car can charge at a rate of 22kW.

    B. The electricity network supports charging at 32A and above, i.e. three-phase 40A and above. 

    However, you can ask the IEC to upgrade the infrastructure, allowing the use of more powerful charging stations: 22kW. 

    Even if the electricity feed currently supports three-phase 25A, it can be expanded through the IEC. The estimated cost of expanding from 25A to 40A is about ₪3,000. 

    All of the above isn't relevant to fast (DC) charging stations, which operate at high charging power of 30-350kW. These stations allow charging about 80 percent of battery capacity within minutes.

  • Deciding the charging station location is an important decision that should be guided by where the car parks and the existing infrastructure.

    The distance of the charging station from the electrical panel matters, as do the car's parking spot and the length of the station's cable, which is usually limited to five meters. 

    If you don't park the car in covered parking, the station needs a high level of water and dust sealing: IP54 and above. At our company all stations are resistant to rain and weather conditions. 

    If the station is installed outside the house, it's important to know that a charging pedestal will usually be needed, and its installation involves an extra charge. 

  • A three-phase connection at home isn't mandatory. There are single-phase charging stations that will charge the car, but charging with them will be slow. Single-phase charging stations are mainly suited to plug-in hybrids.

    If you have the option and the home's infrastructure allows a three-phase connection, it's better to install a three-phase charging station. Such a station allows fast charging of the car. 

    If your car requires a single-phase charging station, chances are that your next car will already need a three-phase charging station, so we recommend saving a future installation and station replacement by installing a three-phase charging station today.

  • When choosing a station, you must take into account:

    1. Is it a fully electric car or a plug-in hybrid: If the car is fully electric, a three-phase station should be installed. If the car is a plug-in hybrid, a single-phase station is enough. 
    2. Does the station include a holder for the charging cable: Stations that provide space for coiling and storing the cable protect it from wear and damage. 
    3. Locking mechanism: If the station will be located outside the house, it's important that it can be locked.
    4. Size and appearance: This is of course a matter of personal taste, but since there's a wide range of charging stations there's no reason to compromise on appearance. 
  • The IP rating is a classification of the degree of protection and sealing of the station against dust and water. The rating consists of the letters IP and two digits, defined by the IEC 60529 standard of the International Electrotechnical Commission. The first digit rates sealing against dust and the second digit rates sealing against water.

    IP54: dust can enter but doesn't interfere with the station. The station is sealed against water at 10 liters/minute at a pressure of 80-100 kilopascals. 

    IP55: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP65: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP67: dust doesn't enter the station. The station is resistant to immersion in water at a depth of 1 meter for 30 minutes.

    Stations installed in an uncovered location should have a sealing level of IP55-67.

  • All the company's products are sold with a 24-month warranty, with the option to extend the warranty up to 60 months.

    If the station is installed by the company's installation team, the customer receives a gift of 12 additional warranty months, for a total of 36 months of warranty. 

    The company allows extending the warranty on stations up to 60 months.

    Because the company is confident in the quality of its products, which have been sold in Europe for many years (France, Germany and more), it offers a warranty extension at a nominal price of ₪499  for an additional 24 months. The warranty extension is possible up to 7 days from the station installation date. 

Accessibility Toolbar