Charging stations for a commercial fleet: AC overnight or DC between shifts? (2026)

How to plan charging stations for a commercial fleet and a logistics center: how many stations, AC overnight or DC between shifts, load management, TOU and per-vehicle management.

In short: In most cases, charging stations for a commercial fleet are 22kW AC stations with load management that charge the vehicles overnight in the parking lot. A 20-60kW DC station is suitable when vehicles return between shifts and need to add dozens of kWh within an hour. In most logistics centers, the right mix is lots of AC and a little DC.

Updated: November 2026

When a fleet of delivery vehicles, pickups or vans switches to electric, the first question isn't which vehicle to buy but how it will be charged. Unplanned charging ends in a line at a single station at six in the morning, or in an expensive connection increase that wasn't necessary. This guide explains how fleet managers and logistics centers plan charging stations for a commercial fleet: how many stations, what power, and how to keep the bill under control.

How do you calculate how much charging the fleet needs each day?

Start with the energy, not the stations. Multiply each vehicle's daily driving by its consumption (kWh per 100 km, based on manufacturer data or fleet data), and you get how many kWh each vehicle needs to add before its next departure.

A kWh is an amount of energy, and a kilowatt (kW) is the charging rate. For example, suppose a vehicle drives 150 km a day and consumes 25 kWh per 100 km: it needs about 37.5 kWh every night. A fleet of 20 such vehicles needs about 750 kWh a day. This is only a sample calculation; the real numbers come from the fleet's driving data.

AC charging overnight or DC charging between shifts?

The decision depends on how long the vehicle stands in the parking lot. A vehicle that returns in the evening and leaves in the morning stands for 10-12 hours, which is enough for a full AC charge. A vehicle that works two shifts stands for an hour or less, and only a DC station will give it enough energy in that time.

Scenario Time parked Recommended solution Estimated energy charged
Deliveries in one shift, return in the evening 10-12 hours A 22kW AC station for each vehicle, with load management Well beyond the daily need, depending on the vehicle's onboard charger
Two shifts, driver change in the parking lot 30-60 minutes A 40-60kW DC station for several vehicles about 20-60 kWh, depending on the power and the vehicle
Service vehicles that return at midday 1–3 hours 22kW AC or 20kW DC about 20-60 kWh
Vehicle taken home overnight Overnight at the employee's home A station at the employee's home with metering for expense reimbursement Depends on the home station

Estimate only, as of November 2026: energy = power times time. Actual power is also limited by the vehicle's onboard charger, and in DC charging the rate drops as the battery fills up.

The differences between AC and DC are explained in detail in the guide DC fast charging station vs. AC.

How many charging stations does a commercial fleet need?

For overnight charging, the simple rule is one station for each vehicle that parks in a fixed spot, or one dual station for every two vehicles. That way no driver has to move a vehicle in the middle of the night, and the system divides the power on its own. DC stations are added according to the number of vehicles working double shifts, not according to the size of the fleet.

In a fleet of 20 vehicles working one shift, that could be 10 dual AC stations. If five of them also work an evening shift, you add one or two DC stations for fast charging at the shift change.

How do you connect many stations without increasing the electrical connection?

With load management. This is a system that divides the available power among the stations charging at that moment, so that total consumption doesn't exceed the connection size. At night there is usually plenty of spare power in the warehouse or factory, and that's exactly when the fleet charges.

In the example of 750 kWh over a 10-hour night, the average power is about 75kW, much less than 20 stations of 22kW running at full power (440kW). With load management, each vehicle gets what it needs by morning, and the connection isn't overloaded. How this works in practice is explained in the guide Load management for charging stations.

How does a TOU tariff affect the fleet's charging costs?

TOU is a tariff based on the time of day: the price per kWh at peak hours is much higher than at off-peak hours. Peak hours apply only on Sunday–Thursday, and on weekends the tariff is off-peak in all seasons. A fleet that charges at night and on weekends is almost always in off-peak hours.

A managed station lets you schedule charging for the cheaper hours and get a consumption report for each vehicle. Details on TOU eligibility for businesses are in the guide How much does it cost to set up a fast-charging station, and an example calculation based on a TOU meter is in the guide Monthly charging report.

Which commercial fleet charging stations are suitable for a logistics center?

Stations managed via OCPP are suitable for a commercial fleet, so that every charging session is assigned to a vehicle and a driver. OCPP is an open communication protocol between the charging station and a cloud management system, enabling permissions, scheduling, reports and remote control. All DSGCharge public stations are managed via OCPP, and the DC stations are ordered with a CCS1 or CCS2 connector according to the vehicles in the fleet.

Model Type and power rating Fleet use Price
Managed charging station 22kW DSG-6012 AC, ‏22kW A fixed parking space for each vehicle, overnight charging ₪3,290
Public dual charging station 22kW DSG-6052 AC, ‏2x22kW Two vehicles per station ₪6,990
Public dual charging station 22kW, floor-standing DSG-6112 AC, ‏2x22kW, floor-standing Open parking lot with no nearby wall ₪7,990
Public DC fast charging station 20kW DSG-5220 DC, ‏20kW Top-up charging at midday ₪15,900
Public DC fast charging station 40kW DSG-5240 DC, ‏40kW Shift change ₪24,900
Public DC fast charging station 60kW DSG-5260 DC, ‏60kW Double shifts and vehicles with a large battery ₪34,990

Store prices are correct as of November 2026, for the station only and without installation. All DC stations in the category DC fast chargers.

Do stations in the fleet's parking lot require a credit card payment terminal?

As a rule, no. Electricity Authority Decision 73006 (31.12.2025, in effect from 26.7.2026) exempts a dedicated charging station, meaning a station that is not open to the public and is intended mainly for employees on site, as well as stations on private premises. The credit card terminal requirement for fast charging stations applies to stations open to the public.

If you want to open some of the stations to customers or the public as well, the rules change. Details in the guide Credit card payment terminal for a charging station.

How do you manage the charging of each vehicle and driver?

In a commercial fleet, it's not enough to know how much electricity was consumed; you need to know which vehicle charged, when and how much. The DSGCharge fleet platform does this with activation by a license plate recognition camera, real-time vehicle data (location, battery, range and speed) and charging metering at the employee's home for expense reimbursement.

Full details on the page EV fleet management, and about camera activation in the guide License plate recognition at a charging station. The stations themselves are managed from the cloud like all OCPP managed stations.

What mistakes should you avoid when planning fleet charging?

Most problems in fleet charging don't come from the stations themselves but from partial planning at the first stage. Four recurring mistakes:

  • Buying DC for everyone: DC stations are more expensive and require a large connection. If the vehicles stand all night, AC stations with load management do the same job at a much lower cost.
  • Connecting stations to an existing panel: According to the Electricity Administration guidelines, each station needs a dedicated circuit. A makeshift connection fails the inspecting electrician's inspection.
  • Planning only for today's vehicles: Fleets grow. Infrastructure that allows stations to be added gradually saves digging and cabling twice.
  • Skipping management: Without assigning charging to vehicles, you can't know what each vehicle costs or identify a vehicle that wasn't charged before a shift.

What is the process for setting up charging for a commercial fleet?

  1. Fleet data: How many vehicles, daily driving, hours parked and shifts.
  2. Electrical check: Connection size, spare power at night and room for a charging panel.
  3. Planning: How many AC stations, whether DC is needed, where each station goes and how to protect it from vehicle impact.
  4. Installation and testing: According to the Electricity Administration guidelines, including an inspecting electrician's check before commissioning.
  5. Connection to management: Permissions for vehicles and drivers, scheduling for off-peak hours and reports.
  6. Service: Fault monitoring and ongoing maintenance.

Read about the requirements for the installation itself in the guide Charging station installation guidelines, and about general planning for a business in the guide Charging stations for businesses.

Who installs and manages charging stations for vehicle fleets in Israel?

DSGCharge is one of Israel's leading companies in EV charging solutions and has been active since 2021. DSGCharge is the importer of its charging stations – the brand is DSGCharge's own. About 20,000 chargers and charging stations have been sold and installed, and its installation and service teams work nationwide.

For vehicle fleets, DSGCharge provides the entire chain: AC and DC stations, installation, load management, a cloud management system developed by the company, a fleet platform and service. That way the fleet manager works with one provider, from planning to the monthly report.

Want a tailored quote?

Send us the number of vehicles, working hours and the size of the electrical connection, and we'll get back to you with an initial plan. You can start with theCharging station installation cost calculator, leave their details or call 077-9920350.

Frequently asked questions

Does a commercial fleet need DC stations?

Not always. A vehicle that stands in the parking lot all night charges well on a 22kW AC station. A 20-60kW DC station is needed mainly when vehicles work two shifts and stand for less than an hour between trips.

How many AC stations are needed per vehicle?

For overnight charging, the rule is one charging point for each vehicle that parks in a fixed spot: a single station per vehicle or a dual station for every two vehicles, with load management dividing the power.

Can you charge 20 vehicles without increasing the electrical connection?

Often, yes. Load management divides the spare power at night among the vehicles, so total consumption stays within the connection's limits. The exact estimate is made after checking the connection and the panel.

Do stations in the fleet's parking lot require a credit card payment terminal?

According to Electricity Authority Decision 73006, a dedicated station that is not open to the public and is intended mainly for employees is exempt, as is a station on private premises. The terminal requirement applies to fast charging stations open to the public.

How do you know how much each vehicle charged?

A station managed via OCPP assigns each charging session to a vehicle or driver, and the DSGCharge fleet platform adds activation by a license plate recognition camera, real-time vehicle data and charging metering at the employee's home.

Share the article:

Already more than

0 +

stations installed

Let us help you

We promise to get back to you in record time with a winning offer!

Which product are you interested in?
  • The cost of a home charging station varies by brand and the station's charging power. There are three charging station power levels: 7kW, 11kW, 22kW (single-phase).

    7kW charging stations are recommended for charging plug-in hybrids (gasoline/diesel-electric) and/or cars that can't charge on three-phase. They aren't recommended for charging an EV, since the time needed to charge an EV will be long. 

    The price of charging stations is affected not only by the station's power but also by whether it has a display and whether it's a smart station managed through a mobile app.

    The price of a simple charging station starts at about ₪1,690 (a promotion at our company for a smart three-phase charging station. The lowest price in Israel!) for 11kW and can reach about ₪4,200 for a 22kW smart station. 

    The price of public charging stations is completely different and is affected by the charging rate, the ability to communicate with computer systems and billing systems. 

    The price of a fast (DC) station runs from tens to hundreds of thousands of shekels.

    The prices above refer to the charging station only and do not include installation. 

  • The cost of charging an EV is significantly lower than fueling a car with a combustion engine (gasoline/diesel). The price per kWh on the residential tariff is 62 agorot (06/2024).

    The cost of driving an EV is around 10% of the cost of driving a combustion-engine car, and that's before accounting for routine servicing, which an EV doesn't need.

    The price of public charging is higher than home charging and is around ₪2.5 per kWh. Despite the higher price at a public station, charging at a public station is still about 60 percent cheaper than fueling a combustion-engine car.  

    There's no doubt that electric charging costs allow cheap driving and may save about ₪15,000 a year, based on driving 20,000 km a year.

    In addition to the savings on driving costs, it's important to emphasize that the annual license fee for an EV is ₪537, while the annual license fee for a combustion-engine and/or plug-in car can reach ₪4,700.

    Bear in mind that the state has already announced that in 2025 a mileage tax (15-25 agorot) will be imposed on EVs. The tax will probably be paid according to the car's odometer at the annual inspection. Even after the mileage tax is imposed, there will be large gaps in driving costs.

  • The cost of installing a home charging station varies by installation location, existing infrastructure, the distance between the electrical panel and the charging station, and the construction work required.

    A distinction should be made between installation in a private house (ground level) and installation in an apartment building. 

    Installation in a private house is simpler, but it too may require laying infrastructure, construction work, chiseling and adjustments.

    Installation in an apartment building is different: it requires a survey of the installation site (virtual/physical) and a signed confirmation that the building committee does not object to the installation. Installation costs in an apartment building are higher than in a private house, and in most cases installation requires construction work, chiseling and adjustments.

    A basic installation starts at ₪2,990 and can reach higher amounts depending on the installation requirements.

    The basic installation price includes laying up to 30 meters of cable. Each additional meter requires an extra charge depending on the station type. In every installation the company installs components in the electrical panel, a circuit breaker and an RCD (Type A), and near the charging station we install an isolating switch. All the company's charging stations are protected against DC leakage current. 

    According to the customer's needs, a meter (kW) can also be installed. A meter is needed when the electricity feeding the station comes from the building's general electrical panel and the building committee must be paid for the electricity consumed. It's important to emphasize that the building committee is not obligated to agree to powering the charging station from the common panel. 

    Each customer can decide whether they want installation by the company and/or prefer to install independently through a certified electrician.

    Installation by the company extends the station's warranty by another year, i.e. 12 additional months.

  • We've encountered quite a few cases where customers living in older houses have a single-phase home electricity network.

     

    The question is whether an EV can be charged from a single-phase home network. The answer is yes, but charging will be slower.

     

    A separate line from the panel must be laid to the charging station. A 16A line allows charging at 3.68kW per hour. A 25A line allows charging at 5.75kW per hour and a 32A line allows charging at 7.4kW.

    EV batteries are typically between 50-80 kWh. 

    This means that if the home had three-phase electricity the car would charge in 5-7 hours, while on a single-phase home network the car can be charged

    16 – 21 hours on a 16A line

    10 – 14 hours on a 32A line.

    Needless to say, the car is usually charged when the battery is around 50%, so the car can also be charged on a home network within one night. 

  • The charging time of the car battery varies by the charging infrastructure and the size of the car's battery.  

    Plug-in hybrid batteries are small batteries that charge on 3.7kW single-phase charging stations within up to three hours. 

    EVs are equipped with larger batteries that can exceed 80kW in cars with a driving range of about 450 km. 

    95% of cars on the market today support a charging rate of 11kW. 

    For a car to charge at a faster rate, two conditions must be met together: 

    A. The car can charge at a rate of 22kW.

    B. The electricity network supports charging at 32A and above, i.e. three-phase 40A and above. 

    However, you can ask the IEC to upgrade the infrastructure, allowing the use of more powerful charging stations: 22kW. 

    Even if the electricity feed currently supports three-phase 25A, it can be expanded through the IEC. The estimated cost of expanding from 25A to 40A is about ₪3,000. 

    All of the above isn't relevant to fast (DC) charging stations, which operate at high charging power of 30-350kW. These stations allow charging about 80 percent of battery capacity within minutes.

  • Deciding the charging station location is an important decision that should be guided by where the car parks and the existing infrastructure.

    The distance of the charging station from the electrical panel matters, as do the car's parking spot and the length of the station's cable, which is usually limited to five meters. 

    If you don't park the car in covered parking, the station needs a high level of water and dust sealing: IP54 and above. At our company all stations are resistant to rain and weather conditions. 

    If the station is installed outside the house, it's important to know that a charging pedestal will usually be needed, and its installation involves an extra charge. 

  • A three-phase connection at home isn't mandatory. There are single-phase charging stations that will charge the car, but charging with them will be slow. Single-phase charging stations are mainly suited to plug-in hybrids.

    If you have the option and the home's infrastructure allows a three-phase connection, it's better to install a three-phase charging station. Such a station allows fast charging of the car. 

    If your car requires a single-phase charging station, chances are that your next car will already need a three-phase charging station, so we recommend saving a future installation and station replacement by installing a three-phase charging station today.

  • When choosing a station, you must take into account:

    1. Is it a fully electric car or a plug-in hybrid: If the car is fully electric, a three-phase station should be installed. If the car is a plug-in hybrid, a single-phase station is enough. 
    2. Does the station include a holder for the charging cable: Stations that provide space for coiling and storing the cable protect it from wear and damage. 
    3. Locking mechanism: If the station will be located outside the house, it's important that it can be locked.
    4. Size and appearance: This is of course a matter of personal taste, but since there's a wide range of charging stations there's no reason to compromise on appearance. 
  • The IP rating is a classification of the degree of protection and sealing of the station against dust and water. The rating consists of the letters IP and two digits, defined by the IEC 60529 standard of the International Electrotechnical Commission. The first digit rates sealing against dust and the second digit rates sealing against water.

    IP54: dust can enter but doesn't interfere with the station. The station is sealed against water at 10 liters/minute at a pressure of 80-100 kilopascals. 

    IP55: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP65: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP67: dust doesn't enter the station. The station is resistant to immersion in water at a depth of 1 meter for 30 minutes.

    Stations installed in an uncovered location should have a sealing level of IP55-67.

  • All the company's products are sold with a 24-month warranty, with the option to extend the warranty up to 60 months.

    If the station is installed by the company's installation team, the customer receives a gift of 12 additional warranty months, for a total of 36 months of warranty. 

    The company allows extending the warranty on stations up to 60 months.

    Because the company is confident in the quality of its products, which have been sold in Europe for many years (France, Germany and more), it offers a warranty extension at a nominal price of ₪499  for an additional 24 months. The warranty extension is possible up to 7 days from the station installation date. 

Accessibility Toolbar