Updated: November 2026
In short: A local authority can set up public charging stations in three main ways: buy and operate them itself, buy them and hand over operation to an operator, or grant an operator the right to use the space in exchange for a revenue split. The engagement is usually subject to tender laws, and from 26.7.2026 the operator must comply with the Electricity Authority rules (Decision 73006).
Charging stations for local authorities have become part of urban planning. The number of electric vehicles in Israel keeps growing, and many residents, especially in high-density housing, have no private parking space where a station can be installed. For the local authority, this is both a service obligation and an opportunity: charging stations in municipal parking facilities, near public institutions and on commercial streets can create a new revenue stream from the parking resource. This guide is intended for city engineers, transportation managers and procurement staff at local authorities, and it explains which models exist, what's worth writing in the tender, how to choose locations and which rules apply to the operator. For the full picture of setup and management, see our page on Setting up public charging stations.
The models and prices of Public charging stations can be found in our store.
Why do charging stations for local authorities matter now?
A resident living in a building without private parking needs a regular, available place to charge. When there are no stations near home, the switch to an electric vehicle is postponed, or the resident depends on distant stations. According to the Knesset Research and Information Center (June 2025), as of April 2025 there were about 8,100 public charging stations operating in Israel: about 1,900 fast (DC) and about 6,200 slow (AC).
Beyond serving residents, charging stations are a planning tool: they let the local authority decide where residents and vehicles will park for long periods, reduce local air pollution and increase the use of existing municipal parking facilities.
Which models are available to a local authority?
No single model suits every local authority. The choice depends on the budget, the authority's operational capacity and how much risk it is willing to take. The table summarizes the four common models:
| Model | Who invests | Who operates | Revenue to the authority | Suitable for… |
|---|---|---|---|---|
| Purchase and self-operation | The Authority | The local authority or a municipal corporation | All the revenue, and all the risk too | A local authority with a parking corporation and operational capacity |
| Purchase + service operator | The Authority | A paid external operator | The revenue minus the operating fee | A local authority that received government support for the purchase |
| Concession / partnership | The operator | The operator | Revenue split or space usage fees | A local authority that doesn't want to invest from its budget |
| Permit to use the space | The operator | The operator | Fixed permit fees | Individual locations, pilot |
In the concession or partnership model, the local authority allocates the space and the connection, and the operator builds, manages and maintains. With DSGCharge, this means no financial investment on the authority's part; the revenue split is determined by the location and subject to a feasibility check.
Does a local authority have to issue a tender?
As a rule, an engagement by a municipality or council is subject to the tender laws that apply to local authorities (including the Municipalities Ordinance and the Municipalities (Tenders) Regulations, 5748-1987), as is the allocation of public space for commercial activity. Many local authorities have already published tenders for setting up and operating charging stations. The exact engagement track (public tender, small tender, exemption or engagement through a municipal corporation) is determined by the authority's legal counsel.
What should you write in the tender documents?
Good tender documents protect residents and the local authority for years. The preparedness guide for local authorities by the Samuel Neaman Institute, funded by the Ministry of Energy (2020), recommends, among other things, these clauses:
- Service level (SLA): quantitative availability metrics, a support center and repair teams available 24/7.
- Open protocol: stations managed via OCPP (an open communication protocol between the station and the management system), so the local authority isn't dependent on a single supplier. A detailed explanation is on the page about OCPP managed stations.
- User identification: avoid identification methods that work with only one operator.
- Data: authority access to usage data, and publishing location, power, availability and tariff to the public.
- Tariffs: a structure that allows a reasonable return on investment for the operator. The guide recommends avoiding free charging in most cases.
- Information security and privacy: cyber protection for the system and protection of user details.
- Smart charging: load management, so that stations can be added without upgrading the connection each time.
- Regulatory compliance: the operator's commitment to comply with the Electricity Authority rules (details below).
How do you choose locations for charging stations in a local authority?
The location determines how much the station will be used, and therefore its profitability. In a dense city, it's worth starting with residential neighborhoods without private parking, and with hubs where people park for an hour or more. In a rural community, a few stations at the community center, the commercial center and tourist sites are enough. As of November 2026:
| Location type | Typical parking time | Recommended station type |
|---|---|---|
| Residential street / neighborhood parking facility | A full night | AC 22kW (dual) |
| Municipal parking facility in the city center | 1-4 hours | AC 22kW + one DC station |
| Community, sports and culture center | 1–3 hours | AC 22kW |
| Industrial and employment zone | Workday | Managed AC 22kW |
| City entrance / main road | 15-40 minutes | DC 60-240kW |
It's recommended to prepare a location map for the entire area of the local authority in advance, mark dedicated parking spaces, and set up enforcement against vehicles that block a station without charging. For high-traffic locations, it's also worth considering a Charging station with an advertising screen, which adds revenue to the station.
Do you need a building permit for a charging station on the street or in a parking facility?
According to the Samuel Neaman Institute preparedness guide (2020), charging stations are defined as “road facilities”, so installing them within a road area by a local authority or a corporation it owns does not require a building permit. A station in a private parking facility doesn't require a permit either. However, the infrastructure works (excavation, laying cables, an electrical cabinet) usually require an excavation permit and coordination with the engineering department, and marking parking spaces and traffic signs may require approval from the traffic sign committee. The rules change, so it's worth checking with the local planning committee before each project.
The installation itself must comply with the Electricity Administration's “Guidelines for Installing an Electric Vehicle Charging System”. At a public AC station the connector is Type 2, and at a DC station the connector is CCS (or CHAdeMO).
Which Electricity Authority rules apply to the station operator?
Electricity Authority Decision 73006 of 31.12.2025 regulates the activity of public charging station operators, and it came into force on 26.7.2026. A local authority choosing an operator must make sure the operator complies with it. The main points of the decision:
| Topic | What was decided | Date |
|---|---|---|
| License | Operators are exempt from a license up to 8 megawatts cumulative; above that a license is required | 26.7.2026 |
| Price display | Slow station: online or next to the station. Fast station: next to the station | 26.7.2026 / 1.1.2028 |
| Payment without registration | Slow station: for example, a QR code or phone. Fast station: credit card payment terminal | 26.7.2026 |
| Credit card payment terminal | New stations put into operation from 1.1.2027; all fast stations from 1.1.2028 | 1.1.2027 / 1.1.2028 |
| Station hogging | Charging for parking without charging is allowed if the customer knows about it in advance | 26.7.2026 |
Is there government support for local authorities?
The Ministry of Energy subsidizes setting up charging stations through calls for proposals and tenders. According to the Knesset Research and Information Center (June 2025), in 2019-2024 about ₪21.4 million was approved for this purpose and about ₪14.8 million was actually spent, and about ₪8.7 million was allocated in the 2025 budget. In one round (reported by ynet in July 2022), 37 local authorities won support of about 70% of the setup cost of 1,122 AC stations for residents without private parking, in public parking facilities and on streets. It's worth following open calls for proposals on the Ministry of Energy website and preparing a location map in advance, so you can apply quickly.
Which stations suit a local authority?
All DSGCharge public stations are managed via OCPP from a cloud system, and DC stations are ordered with a CCS1 or CCS2 connector, your choice. Prices from the store, as of November 2026:
| Model | Type | Suitable use in a local authority | Price |
|---|---|---|---|
| DSG-6052 | Dual AC 2x22kW | Municipal and neighborhood parking facilities | ₪6,990 |
| DSG-6112 | Dual floor-standing AC 22kW | Streets and open parking lots | ₪7,990 |
| DSG-6012 | Managed AC 22kW | Employee parking facilities and public buildings | ₪3,290 |
| DSG-5240 | DC 40kW | Commercial centers and small parking facilities | ₪24,900 |
| DSG-5260 | DC 60kW | Central parking facility, city entrance | ₪34,990 |
| DSG-7420 / DSG-7480 / DSG-7540 | DC 120 / 180 / 240kW | Main roads and charging hubs | By quote |
For city entrance locations, it's also worth reading the guide toUltra-fast charging station, and the cost breakdown in theHow much does it cost to set up a fast-charging station. For a comparison between the dual stations, see Public dual charging station 22kW. You can estimate the installation cost for each location with theinstallation cost calculator.
What does DSGCharge provide to local authorities?
DSGCharge is one of Israel's leading companies in EV charging solutions. DSGCharge is the importer of its charging stations – the brand is DSGCharge's own. The company has been active since 2021, with about 20,000 chargers and charging stations sold and installed, and installation and service teams nationwide.
For local authorities, DSGCharge provides an end-to-end project: location survey, electrical design, supply of AC and DC stations, installation, maintenance, and also Public charging station management system: cloud management, a resident app, payment terminals, license plate recognition cameras and reports for the authority. The system was developed in-house by DSGCharge and can be customized and branded to the customer's requirements, so the stations can appear under the municipality's name. You can work under a purchase model or a partnership model, as also described in the guide Charging stations for parking facilities.
Frequently asked questions
Can a local authority set up charging stations without investing from its budget?
Yes. In a concession or partnership model, the operator invests in the stations and infrastructure, and the local authority allocates space. With DSGCharge there is no financial investment on the authority's part; the revenue split is determined by the location and subject to a feasibility check.
Does a charging station on the street need a building permit?
According to the Samuel Neaman Institute guide (2020), a charging station is a “road facility”, and installing it within a road area by a local authority does not require a building permit. The excavation and electrical works still require permits and coordination, so it's worth checking with the local planning committee.
Which rules apply to public station operators from 2026?
Electricity Authority Decision 73006 came into force on 26.7.2026: price display, an option to pay without registration, and a license exemption up to 8 megawatts. A credit card payment terminal is required at new fast charging stations from 1.1.2027 and at all fast charging stations from 1.1.2028.
Which station suits a municipal parking facility?
In a parking facility where vehicles park for several hours or a whole night, a dual AC 22kW station such as the DSG-6052 (₪6,990, as of November 2026) gives the lowest cost per charging point. In a central parking facility, it's worth adding one DC station for fast charging.
Does the Ministry of Energy support local authorities that set up charging stations?
Yes, through calls for proposals and tenders. In a round reported in 2022, 37 local authorities won support of about 70% of the setup cost. About ₪8.7 million was allocated in the 2025 budget to support charging stations (Knesset Research and Information Center).
Want to plan charging stations in your local authority?
The DSGCharge team will build a location map with you, propose a business model and prepare a technical specification for the tender. leave your details or call 077-9920350.
Sources: Electricity Authority Decision 73006 (31.12.2025); Knesset Research and Information Center, analysis of the Ministry of Energy budget (June 2025); Samuel Neaman Institute, Preparedness Guide for Private Electric Transportation for Local Authorities, second edition (2020, funded by the Ministry of Energy); ynet, “The Ministry of Energy will subsidize the setup of additional public charging stations” (31.7.2022). All information as of November 2026.