Anyone planning a fast charging station at a fuel station, parking facility, mall, hotel or along a highway quickly discovers that the station's price is just one line in the budget. This guide breaks down the cost of setting up a fast charging station into its components: hardware, electrical connection, infrastructure and works, operation and payment processing system, approvals, maintenance and ongoing electricity. That way you can build a real budget and compare quotes.
In short: The cost of setting up a fast charging station consists of seven main components. Hardware starts at ₪24,900 for a 40kW public DC charging station and ₪34,990 for a 60kW station (store prices, November 2026). Stations from 120kW up to 480kW and above are sold by quote. On top of that come the electrical connection, infrastructure, operating system, approvals and maintenance, and they often cost more than the station itself.
You can compare DSGCharge DC charging stations, from 20kW to 60kW with a choice of CCS1 or CCS2, on the page DC fast chargers.
What does the cost of setting up a fast charging station include?
A fast charging station is an infrastructure project, not the purchase of a device. The budget includes the stations, the electricity that supplies them, the on-site works, the system that operates them and collects payment, and service over the years. The difference between quotes from different suppliers usually stems from the components that weren't included in them.
DC fast charging station is a station that converts alternating current from the grid into direct current (DC) inside the station, and feeds it directly into the vehicle's battery. That's why it can deliver tens and hundreds of kilowatts (kW), compared with an AC charging station, which is limited by the vehicle's on-board charger. For the full buying guide by power, see DC fast charging station.
| Budget component | What it includes | What the price depends on |
|---|---|---|
| 1. Charging stations (hardware) | DC charging stations, and sometimes also complementary AC charging stations | Power, number of connectors, CCS1 or CCS2 connector, screen, payment terminal |
| 2. Electrical connection | A connection upgrade or a new connection from the IEC, and sometimes a transformer | The total power, the grid in the area, the Electricity Authority's tariff book |
| 3. Electrical planning and infrastructure | Planning, electrical panel, protections, supply cables, earthing | Distance from the panel, cable cross-section, number of stations |
| 4. Civil works and parking accessories | Foundation, excavation, conduits, asphalt, protective bollards, marking and signage | Type of ground, length of excavation, accessibility requirements at the site |
| 5. Operation and payment processing system | Cloud management via OCPP, app, credit card payment terminal, communication | Number of stations, operating model, branding requirements |
| 6. Inspections and approvals | Inspection by an inspecting electrician, coordination with the IEC and the local authority | Size of the installation, permits required at the site |
| 7. Ongoing operation | Electricity, maintenance, communication, service and availability | Electricity tariff (including TOU), level of use, service agreement |
As of November 2026. Exact prices for each component are given only after a site survey.
How much does a DC fast charging station itself cost?
The hardware price depends mainly on the power. In the DSGCharge store, the prices of the public charging stations are (as of November 2026, for the station only, excluding installation):
| Model | Power | Best for | Store price |
|---|---|---|---|
| DSG-5240 | DC 40kW | Parking facilities, businesses, vehicle fleets, stays of an hour or more | ₪24,900 |
| DSG-5260 | DC 60kW | Malls, hotels, urban fuel stations | ₪34,990 |
| DSG-7420 | DC 120kW | Fuel stations, highways, short stops | By quote |
| DSG-7480 / DSG-7540 | DC 180kW / 240kW | Charging hubs on main highways | By quote |
| DSG-6052 | Dual AC 22kW | A complementary station for long stays | ₪6,990 |
All DSGCharge public charging stations are managed via OCPP from a cloud computing system, and the DC charging stations are ordered with a choice of CCS1 or CCS2 connector. CCS2 is the common plug in Israel for fast charging; CCS1 is needed mainly for pickups and American vehicles. In large projects, DC charging stations with power of up to 480kW are available.
How much does the electrical connection for a fast charging station cost?
The electrical connection is the component that's hardest to estimate in advance, because it depends on the condition of the grid in the area and the existing connection at the site. The payment to the Israel Electric Corporation (IEC) for a new connection or a connection upgrade is set according to the Electricity Authority's tariff book (chapter 4, connection tariffs, including a dedicated table for industrial and commercial buildings), so it isn't open to negotiation with the supplier.
To understand the order of magnitude, it helps to translate power into current. At a three-phase voltage of 400 volts, every 10kW requires roughly 14-15 amps per phase:
- A 60kW station: roughly 90 amps per phase.
- A 120kW station: roughly 175 amps per phase.
- Two 120kW stations or one 240kW station: roughly 350 amps per phase.
The larger the existing connection at the site, the smaller the addition. At high power levels, a high-voltage connection and a dedicated transformer may be needed, which change the budget significantly. That's why the first step in any project is checking the existing connection against the planned power.
Load management (dynamic distribution of the available power among the stations) can save a connection upgrade: for example, two stations that share power when they operate together and receive full power when only one is in use.
What infrastructure and works costs should you budget for?
Infrastructure costs are determined mainly by the distance between the electrical panel and the stations. At DC power levels the cables are thick and expensive, so every meter of excavation and cable affects the price. The cheapest location is usually the one closest to the panel, provided it's convenient and accessible for drivers.
- Electrical design and coordinating the supply with the existing panel.
- Panel, circuit breakers and protections, including an RCD and earthing according to the Electricity Administration's guidelines (November 2025).
- Concrete foundation for a free-standing station, excavation, conduits and asphalt restoration.
- Parking accessories: protective bollards, stoppers, parking space marking, lighting and signage. For details, see the guide toCharging station cabinet and parking accessories.
For an initial estimate of the installation cost by distance and power, use theCharging station installation cost calculator.
How much do the operating system, payment processing and app cost?
A public station needs a system that operates the stations, collects payment, displays price and availability and reports faults. OCPP (Open Charge Point Protocol) is an open communication protocol between the station and the cloud management system, which enables remote control, permissions, pricing and reports.
According to Electricity Authority decision 73006 (31.12.2025, in effect from 26.7.2026), fast and ultra-fast charging stations must have a credit card payment terminal that allows payment without registration and without an app: at new stations from 1.1.2027, and at all stations from 1.1.2028. In its regulatory analysis of the decision, the Authority estimates the cost of the terminal at “thousands of shekels per station.”
DSGCharge supplies Public charging station management system in full: cloud management, a user app, payment terminals, license plate recognition cameras, pricing, payment processing and reports. All the systems are developed in-house by DSGCharge and can be customized and branded to the customer's requirements (White Label). For an explanation of the protocol, see OCPP managed stations.
Which approvals and regulatory requirements affect the cost?
Electricity Authority decision 73006 sets a framework for operators of public charging stations. An operator with a total capacity of up to 8 megawatts is exempt from a license, subject to the exemption rules; above 8 megawatts, a license is required. According to the Authority, 8 megawatts is roughly 50 DC fast charging stations, so most location owners will fall within the exemption.
The requirements that affect the budget:
- Clear price display near the station.
- A credit card payment terminal at fast charging stations (according to the timetable above).
- Availability information that reflects the station's working condition.
- No discrimination between occasional and regular customers.
- Compliance with the Ministry of Energy's cybersecurity guidelines.
In addition, an inspection by an inspecting electrician is required before commissioning. DSGCharge products have Standards Institution of Israel (SII) approvals.
What does the ongoing operation of a fast charging station cost?
The big ongoing cost is electricity. According to the Electricity Authority's tariff book (July 2026), the TOU tariff also applies to low-voltage consumers connected with a connection of 3×200 amps or more and consuming more than 40,000 kWh per year. TOU tariff (load and time tariff) is a tariff in which the price per kWh changes by season and hour. Peak hours apply only Sunday-Thursday, and weekends are off-peak hours in all seasons.
Beyond electricity, budget for cellular communication for the stations, licensing or a subscription to the management system, payment processing fees, preventive maintenance and service calls. Depending on usage, it's also worth considering a warranty extension.
Example: what does a budget for a mall parking facility look like?
Suppose a mall wants to start with two 60kW DC charging stations for short visits and two 22kW dual AC charging stations for long stays. The hardware component alone, according to store prices in November 2026:
| Item | Quantity | Price per unit | Total |
|---|---|---|---|
| DSG-5260 public DC charging station 60kW | 2 | ₪34,990 | ₪69,980 |
| DSG-6052 public dual AC charging station 22kW | 2 | ₪6,990 | ₪13,980 |
| Total hardware | ₪83,960 |
To this amount will be added the electrical connection, infrastructure, works, operating system and approvals. With load management, you can start with a smaller connection and upgrade later, according to actual usage.
What should you ask for in a quote to compare properly?
Quotes for a fast charging station look very different from one another, because each supplier includes different components. Ask that each quote itemize separately:
- Model, power, number of connectors and connector type (CCS1 or CCS2) for each station.
- Whether the payment to the IEC is included, or is your responsibility.
- The length of cables and excavation that was priced, and the price per additional meter.
- The management system: does it support OCPP, how much does it cost per month, and what do the payment terminal and app include.
- Warranty terms, fault response times and spare parts stock in Israel.
How do you lower the setup cost?
- Match the power to the length of stay. In a parking facility where people stay for two hours, a 40-60kW station and complementary AC charging stations will be enough, and there's no need for 240kW. The guide toCharging stations for parking facilities details the match by parking facility type.
- Place close to the panel to shorten cables and excavation.
- Users with load management before upgrading the connection.
- Plan in stages: Lay infrastructure for future stations already during the first excavation.
- Consider a partnership: Location owners can set up stations with DSGCharge with no financial investment on their part. The revenue split is determined by the location and is subject to a feasibility check.
Who builds fast charging stations in Israel end to end?
DSGCharge is one of Israel's leading companies in EV charging solutions. DSGCharge is the importer of its charging stations – the brand is DSGCharge's own. The company has been active since 2021, and about 20,000 chargers and charging stations have been sold and installed, with installation and service teams nationwide.
In a fast charging station project, DSGCharge accompanies all the stages: site survey, choice of stations, electrical planning, installation, operation and payment processing system, and service and maintenance. For details on the service, see Setting up public charging stations.
Want a budget for your site? leave your details or call 077-9920350, and we'll get back to you with a site survey and a detailed quote for each component.
Frequently asked questions
How much does it cost to set up a fast charging station?
There's no single price. Hardware starts at ₪24,900 for a 40kW DC charging station and ₪34,990 for a 60kW station (in the DSGCharge store, November 2026). The electrical connection, infrastructure, operating system and approvals are priced according to the site, after a survey.
What is the most expensive component of a fast charging station?
At high power levels, the electrical connection and infrastructure often cost more than the stations themselves, especially when a significant connection upgrade or a transformer is required.
Is a credit card payment terminal mandatory at a DC fast charging station?
Yes. According to Electricity Authority decision 73006, new fast and ultra-fast charging stations require a credit card payment terminal from 1.1.2027, and all stations from 1.1.2028.
Do you need a license to operate public charging stations?
An operator with a total capacity of up to 8 megawatts is exempt from a license, subject to the Electricity Authority's exemption rules. Above 8 megawatts, a license is required.
Can you set up a charging station without investing?
Location owners can set up stations with DSGCharge in a partnership model, with no financial investment on their part. The revenue split is determined by the location and is subject to a feasibility check.