A commercial parking facility in planning: why you should think about EV charging at the design stage, not after the concrete has set

A guide for owners of new commercial parking facilities: why planning charging infrastructure at the engineering design stage saves future costs, which details to mark in advance, and how to avoid infrastructure that falls short of future needs.
A commercial parking facility in planning: why you should think about EV charging at the design stage, not after the concrete has set

You are planning a new commercial parking facility, and the architect or engineer asks you “How many charging stations do you want at this stage?” – and the honest answer is that it's not clear yet. This is exactly the point where many projects miss out. Not because there is no intention to install charging stations, but because the question is asked too late, or the answer given refers only to what is needed “now”, without thinking about what will be required two or three years from now.

This problem recurs especially in commercial parking facilities – malls, shopping centers, office buildings with shared parking, or public parking areas. The stage of infrastructure work, excavation, electrical design and conduits happens once. After the concrete is poured, the trenches are closed and the panels are in place – every change becomes complex, expensive and sometimes involves dismantling finishing work that has already been completed.

The difference between planning infrastructure in advance and retrofitting

There is a fundamental difference between two situations: one is planning infrastructure in advance that takes future upgrades into account, and the other is trying to “add charging stations” to a parking facility that was never built with charging in mind. In the first situation, the infrastructure designer can mark, already at the engineering stage, locations for electrical panels, a cabling route, space for buried conduits, and even an electrical capacity reserve – without actually installing any station. In the second situation, every intervention in existing infrastructure involves dismantling trenches, cutting into concrete that has already been poured, re-excavation, and an electrical connection that has to be “hidden” in an existing structure. This difference is not a minor technical matter – it is the difference between a project that runs on a planned budget and a project that runs into unplanned work midway.

What to take into account at the engineering design stage

At the stage when the parking facility is still being planned on paper – whether it is an underground garage, a multi-story garage or an open parking area – there are several parameters worth clarifying with the professional accompanying the project, even before ordering any charging station:

  • Location of the electrical panels and the distance from them – a long distance from the electrical panel to the future stations affects the cabling length, the type of trenches required and sometimes also the cable cross-section. Planning the right panel locations already at the engineering stage can save unnecessary infrastructure work later.
  • Electrical capacity reserve – it is important to check with the project's electrical engineer whether a capacity reserve for future charging stations is possible, so that there will be no need to upgrade the grid connection at a later stage.
  • Trench routes and buried conduits – even if no stations are actually installed on day one, you can lay conduits and empty pipes (without cabling) along pre-marked routes, so that in the future the cabling itself will be the only work required.
  • Division by parking zones – in a large commercial parking facility, it is worth deciding already at the planning stage which zones are intended for charging (for example, an employee parking zone alongside a public parking zone), so that the infrastructure suits the expected type of use in each zone.
Keep in mind: A professional infrastructure check before installation is not a step you can skip. Even if you intend to install only one or two charging stations in the first phase, the infrastructure check at the engineering design stage is the opportunity to make sure that the location, the electrical reserve and the buried route are also suitable for future expansion.

Planning for a future number of stations, not just the current need

A question that comes up again and again in planning discussions: “Why plan for more stations than I need now?” The answer is simple – because demand for charging in commercial parking facilities tends to grow over time, and the cost difference between proper planning in advance and a retrofit is especially significant when the infrastructure work has already been closed up. The key point is not to actually install more stations than you need today, but to plan the infrastructure – the conduits, the routes, the capacity reserve and the panel locations – so that adding stations in the future will be simple cabling work and not a new infrastructure project. In this context, DSGCharge accompanies such projects through a professional infrastructure check at the planning stage, which looks not only at the immediate need but also at reasonable expansion scenarios – whether it is adding AC stations to an employee parking area, or at a more advanced stage also examining DC fast charging stations in zones that require a shorter charging time.

The connection between early planning and a charging management system

In a commercial parking facility, it is not enough to install a charging station – you also need to know who uses it, how billing works, and how to prevent a situation where one station “grabs” all the available power while other stations stand empty. That is why infrastructure planning in a commercial parking facility should include, at an early stage, thought about a suitable charging management system. Load management system makes it possible to divide the existing power among several stations dynamically, so there is no need to bring huge electrical capacity to each station separately – but rather to manage what exists intelligently. This is especially relevant in a commercial parking facility where the number of users changes during the day, and sometimes also between weekdays and weekends. In addition, when the parking facility belongs to a business, a mall or a building committee, it is also relevant to examine aspects of user management, payment processing and billing – who can use the station, how payment is made, and how employee charging is separated from public charging. Alongside its charging stations, DSGCharge also offers managed charging systems for buildings, parking facilities andVehicle fleet, including load management, monitoring and an infrastructure solution that suits future growth in the number of electric vehicles in the parking facility.

About DSGCharge – for details on the company's approach to planning end-to-end charging solutions, including infrastructure checks, installation and management.

When to involve DSGCharge in the process

The earlier the planning takes place – when the engineering plans are still on paper and no infrastructure work has yet been done on site – the easier it is to adapt the plan to future needs without affecting the project's schedule or costs. That is why it is recommended to involve a professional who knows the charging field already at the stage when decisions are made about the location of the electrical panels, trench routes and the division of parking zones. DSGCharge specializes in the planning and installation of EV charging stations nationwide, adapted to the private, business and public sectors – including parking facilities, shopping centers, building committees and office buildings. In an initial consultation call, you can review the existing plans, understand expectations regarding the number of electric vehicles expected to use the parking facility, and get a clear direction on what is worth planning in advance so you don't get stuck with infrastructure that won't be enough. It is important to note – the final price of a charging infrastructure planning and installation project varies according to the type of station, the required power, the distance from the electrical panel, single-phase or three-phase, the need for trenches, cutting or excavation, a load management system, communication and payment processing, and the overall complexity of the installation. Every commercial parking project is different, and the right fit starts with an infrastructure check, not a generic quote.

Professional tip: If the project is still at the engineering design stage, ask the professional designing the infrastructure to leave an electrical “opening” – a capacity reserve and free trench routes – even if you actually intend to install only one or two stations in the first phase. That is the difference between a simple expansion and redoing the infrastructure work.

If you are in the process of planning a new commercial parking facility, or the engineering work has not yet been completed, now is the right time to look into the issue – and not after the concrete has already set. You can browse the existing solutions inEV charging stations or also look into the related need forEV charging cables, but the recommended first step is a conversation with DSGCharge to understand what suits your specific project.

Want to review the plans for your commercial parking facility before continuing with the infrastructure work? You can contactDSGCharge for advice and a charging solution that takes into account both today and what will come in two or three years.

📊 In brief: key points of the article

1

The difference between planning infrastructure in advance and retrofitting

There is a fundamental difference between two situations: one is planning infrastructure in advance that takes future upgrades into account, and the other is trying to "add charging stations" to a parking facility that was never built…

2

What to take into account at the engineering design stage

At the stage when the parking facility is still being planned on paper – whether it is an underground garage, a multi-story garage or an open parking area – there are several parameters worth clarifying with the professional accompanying…

3

Planning for a future number of stations, not just the current need

A question that comes up again and again in planning discussions: "Why plan for more stations than I need now?" The answer is simple – because demand for charging in commercial parking facilities tends to grow over time,…

FAQ

When is the right time to start planning charging infrastructure in a new commercial parking facility?
The ideal time is at the engineering design stage, before the concrete is poured and the trenches are closed. Once engineering design is underway, you can mark locations for electrical panels, trench routes and a capacity reserve without significant additional cost, whereas a retrofit may require cutting or new excavation.

Do all the stations need to be installed in the first phase?
Not necessarily. You can install in the first phase only the number of stations actually required, but plan the infrastructure – the conduits, the potential cabling and the capacity reserve – so that future expansion is simple and does not require dismantling finishing work.

What is the difference between planning infrastructure in advance and adding stations retroactively?
Planning in advance makes it possible to leave trench routes and buried conduits free during construction, so that in the future only cabling work is needed. A retrofit usually involves cutting into existing concrete, dismantling trenches and additional infrastructure work that make the project more expensive and complicated.

Does a commercial parking facility need a load management system, or is a single charging station enough?
When several charging stations are planned in a parking facility, a load management system makes it possible to divide the existing power among the stations dynamically, so there is no need to increase the total electrical capacity for each station separately. This is especially relevant in commercial parking facilities with usage that changes during the day.

How can DSGCharge help at the planning stage, before a charging station is actually installed?
DSGCharge carries out a professional infrastructure check and accompanies the engineering design stage, so that the location, routes and capacity reserve suit both the current need and future expansion. This prevents a situation where infrastructure that has already been completed has to be changed.

What do you do after the parking facility is built?

Once the infrastructure is ready, you can choose an operating model: stations owned by the parking facility, a partnership with DSGCharge with no financial investment on your part (revenue sharing is determined by location and subject to a feasibility check), or purchasing AC and DC stations. The full comparison of the models is in the guide Charging stations for parking facilities. Payment processing, the app and reports are run by the charging station operations system from DSGCharge.

Share the article:

Already more than

0 +

stations installed

Let us help you

We promise to get back to you in record time with a winning offer!

Which product are you interested in?
  • The cost of a home charging station varies by brand and the station's charging power. There are three charging station power levels: 7kW, 11kW, 22kW (single-phase).

    7kW charging stations are recommended for charging plug-in hybrids (gasoline/diesel-electric) and/or cars that can't charge on three-phase. They aren't recommended for charging an EV, since the time needed to charge an EV will be long. 

    The price of charging stations is affected not only by the station's power but also by whether it has a display and whether it's a smart station managed through a mobile app.

    The price of a simple charging station starts at about ₪1,690 (a promotion at our company for a smart three-phase charging station. The lowest price in Israel!) for 11kW and can reach about ₪4,200 for a 22kW smart station. 

    The price of public charging stations is completely different and is affected by the charging rate, the ability to communicate with computer systems and billing systems. 

    The price of a fast (DC) station runs from tens to hundreds of thousands of shekels.

    The prices above refer to the charging station only and do not include installation. 

  • The cost of charging an EV is significantly lower than fueling a car with a combustion engine (gasoline/diesel). The price per kWh on the residential tariff is 62 agorot (06/2024).

    The cost of driving an EV is around 10% of the cost of driving a combustion-engine car, and that's before accounting for routine servicing, which an EV doesn't need.

    The price of public charging is higher than home charging and is around ₪2.5 per kWh. Despite the higher price at a public station, charging at a public station is still about 60 percent cheaper than fueling a combustion-engine car.  

    There's no doubt that electric charging costs allow cheap driving and may save about ₪15,000 a year, based on driving 20,000 km a year.

    In addition to the savings on driving costs, it's important to emphasize that the annual license fee for an EV is ₪537, while the annual license fee for a combustion-engine and/or plug-in car can reach ₪4,700.

    Bear in mind that the state has already announced that in 2025 a mileage tax (15-25 agorot) will be imposed on EVs. The tax will probably be paid according to the car's odometer at the annual inspection. Even after the mileage tax is imposed, there will be large gaps in driving costs.

  • The cost of installing a home charging station varies by installation location, existing infrastructure, the distance between the electrical panel and the charging station, and the construction work required.

    A distinction should be made between installation in a private house (ground level) and installation in an apartment building. 

    Installation in a private house is simpler, but it too may require laying infrastructure, construction work, chiseling and adjustments.

    Installation in an apartment building is different: it requires a survey of the installation site (virtual/physical) and a signed confirmation that the building committee does not object to the installation. Installation costs in an apartment building are higher than in a private house, and in most cases installation requires construction work, chiseling and adjustments.

    A basic installation starts at ₪2,990 and can reach higher amounts depending on the installation requirements.

    The basic installation price includes laying up to 30 meters of cable. Each additional meter requires an extra charge depending on the station type. In every installation the company installs components in the electrical panel, a circuit breaker and an RCD (Type A), and near the charging station we install an isolating switch. All the company's charging stations are protected against DC leakage current. 

    According to the customer's needs, a meter (kW) can also be installed. A meter is needed when the electricity feeding the station comes from the building's general electrical panel and the building committee must be paid for the electricity consumed. It's important to emphasize that the building committee is not obligated to agree to powering the charging station from the common panel. 

    Each customer can decide whether they want installation by the company and/or prefer to install independently through a certified electrician.

    Installation by the company extends the station's warranty by another year, i.e. 12 additional months.

  • We've encountered quite a few cases where customers living in older houses have a single-phase home electricity network.

     

    The question is whether an EV can be charged from a single-phase home network. The answer is yes, but charging will be slower.

     

    A separate line from the panel must be laid to the charging station. A 16A line allows charging at 3.68kW per hour. A 25A line allows charging at 5.75kW per hour and a 32A line allows charging at 7.4kW.

    EV batteries are typically between 50-80 kWh. 

    This means that if the home had three-phase electricity the car would charge in 5-7 hours, while on a single-phase home network the car can be charged

    16 – 21 hours on a 16A line

    10 – 14 hours on a 32A line.

    Needless to say, the car is usually charged when the battery is around 50%, so the car can also be charged on a home network within one night. 

  • The charging time of the car battery varies by the charging infrastructure and the size of the car's battery.  

    Plug-in hybrid batteries are small batteries that charge on 3.7kW single-phase charging stations within up to three hours. 

    EVs are equipped with larger batteries that can exceed 80kW in cars with a driving range of about 450 km. 

    95% of cars on the market today support a charging rate of 11kW. 

    For a car to charge at a faster rate, two conditions must be met together: 

    A. The car can charge at a rate of 22kW.

    B. The electricity network supports charging at 32A and above, i.e. three-phase 40A and above. 

    However, you can ask the IEC to upgrade the infrastructure, allowing the use of more powerful charging stations: 22kW. 

    Even if the electricity feed currently supports three-phase 25A, it can be expanded through the IEC. The estimated cost of expanding from 25A to 40A is about ₪3,000. 

    All of the above isn't relevant to fast (DC) charging stations, which operate at high charging power of 30-350kW. These stations allow charging about 80 percent of battery capacity within minutes.

  • Deciding the charging station location is an important decision that should be guided by where the car parks and the existing infrastructure.

    The distance of the charging station from the electrical panel matters, as do the car's parking spot and the length of the station's cable, which is usually limited to five meters. 

    If you don't park the car in covered parking, the station needs a high level of water and dust sealing: IP54 and above. At our company all stations are resistant to rain and weather conditions. 

    If the station is installed outside the house, it's important to know that a charging pedestal will usually be needed, and its installation involves an extra charge. 

  • A three-phase connection at home isn't mandatory. There are single-phase charging stations that will charge the car, but charging with them will be slow. Single-phase charging stations are mainly suited to plug-in hybrids.

    If you have the option and the home's infrastructure allows a three-phase connection, it's better to install a three-phase charging station. Such a station allows fast charging of the car. 

    If your car requires a single-phase charging station, chances are that your next car will already need a three-phase charging station, so we recommend saving a future installation and station replacement by installing a three-phase charging station today.

  • When choosing a station, you must take into account:

    1. Is it a fully electric car or a plug-in hybrid: If the car is fully electric, a three-phase station should be installed. If the car is a plug-in hybrid, a single-phase station is enough. 
    2. Does the station include a holder for the charging cable: Stations that provide space for coiling and storing the cable protect it from wear and damage. 
    3. Locking mechanism: If the station will be located outside the house, it's important that it can be locked.
    4. Size and appearance: This is of course a matter of personal taste, but since there's a wide range of charging stations there's no reason to compromise on appearance. 
  • The IP rating is a classification of the degree of protection and sealing of the station against dust and water. The rating consists of the letters IP and two digits, defined by the IEC 60529 standard of the International Electrotechnical Commission. The first digit rates sealing against dust and the second digit rates sealing against water.

    IP54: dust can enter but doesn't interfere with the station. The station is sealed against water at 10 liters/minute at a pressure of 80-100 kilopascals. 

    IP55: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP65: dust doesn't enter the station. The station is resistant to water at 12.5 liters/minute at a pressure of 30 kilopascals from a distance of 3 meters.

    IP67: dust doesn't enter the station. The station is resistant to immersion in water at a depth of 1 meter for 30 minutes.

    Stations installed in an uncovered location should have a sealing level of IP55-67.

  • All the company's products are sold with a 24-month warranty, with the option to extend the warranty up to 60 months.

    If the station is installed by the company's installation team, the customer receives a gift of 12 additional warranty months, for a total of 36 months of warranty. 

    The company allows extending the warranty on stations up to 60 months.

    Because the company is confident in the quality of its products, which have been sold in Europe for many years (France, Germany and more), it offers a warranty extension at a nominal price of ₪499  for an additional 24 months. The warranty extension is possible up to 7 days from the station installation date. 